Angus Place East Project

Centennial Coal

This project will be completed in March 2015 and included the design, construction and commissioning of the following;

  • 66kV ASP1 Contestable Works – 66kV Endeavour Energy Supply Point
  • Substation 0 – 66kV Endeavour Energy Switching Station
  • 66kV Transmission Lines – 4.5km of buried 66kV cables, earth cables and fibre optic communications cables
  • Substation 1 – 66/11kV 15MVA Substation
  • 11kV Transmission Lines – 1km of buried 11kV cables, earth cables and fibre optic communications cables
  • Substation 2 – 11kV Switchroom
  • 11kV Borehole Cables – 400m of suspended 11kV cables, fibre optic communications cables, telephone cables and control cables
  • Substation 3 – Pit Bottom 11kV Switchboard
  • PLC, SCADA and HMI systems integration
  • Earthing systems 

 

Narrabri Coal Project

Whitehaven Coal

This project was completed in 2012 and included the design, construction and commissioning of the following;

  • 66/11kV Twin 10MVA Substation
  • Buried 11kV cables, earth cables and fibre optic communications cables across the site
  • Vent Fan 11kV Switchroom
  • 11kV/415V Distribution Substations across the site
  • PLC, SCADA and HMI systems integration
  • Earthing systems
 
 

Airly Mine Project

Centennial Coal

This project will be completed in 2010 and included the design, construction and commissioning of the following;

  • 66kV ASP1 Contestable Works – 66kV Endeavour Energy Supply Point
  • Substation 0 – 66kV Endeavour Energy Switching Station
  • Substation 1 – 66/11kV 16MVA Substation
  • 11kV Transmission Lines – Buried 11kV cables, earth cables and fibre optic communications cables across the site
  • Substation 2 – 11/415V 2.5MVA Substation and 415V Switchroom
  • 11kV Power Factor Correction
  • PLC, SCADA and HMI systems integration
  • Earthing systems
 
 

Abel Mine Project

Donaldson Coal

This project will be completed in 2010 and included the design, construction and commissioning of the following;

  • 33/11kV Twin 10MVA Substation
  • Buried 11kV cables, earth cables and fibre optic communications cables across the site
  • Boxcut 11kV Switchroom
  • 11kV/415V Distribution Substations across the site
  • PLC, SCADA and HMI systems integration
  • Earthing systems